◆ Scope & Progress · Customer View

UPW Skid Module Fabrication — Scope & Progress

Okland Construction Co. · Minneapolis, MN · Job → Area → Train → Skid → Spool · weighted by spool count
OKLAND CONSTRUCTION
Scope & Progress Tracker

📦 Scope by Area

click an area to filter the breakdown below

🧱 Skid Breakdown & Progress

Set each skid's current phase — progress is credited per the Okland rules of credit (Material Receiving 10% → Spool Kits 25% → Fabrication 55% → Pre-Install QC 60% → Installation 85% → Post-Install QC 90% → Final Testing 95% → Shipping 100%) and rolls up weighted by spool count to Train, Area, and the whole Job. Updates save automatically in this browser.

📅 Train 2 — Commitment Dates & IFC Status

Draft · updated 6/23/26 · L20